Expansion Phases

Since the start of the Arab petroleum pipeline company “SUMED” the company has been continuously expanding to meet the market demand

 

  • The first expansion phase was in 1989/1990 by adding an additional storage of 618,000 cbm through the construction of 3 floating roof storage tanks in Sidi Kerir of capacity 103,000 cbm each and 3 storage tanks of the same type and capacity in Ain Sukhna.

  • The second expansion phase was in 1997 by adding a total capacity of 702,000 cbm through the construction of 6 floating roof storage tanks in Sidi Kerir of capacity 117,000 cbm each and a 3 MW boosting pumping station.

  • The third expansion phase was in 2005 which introduced an additional storage of 351,000 cbm through the construction of 3 floating roof storage tanks in Sidi Kerir of capacity 117,000 cbm each.

  • In 2008 the fourth expansion phase was commissioned by building 5 floating roof storage tanks in Sidi Kerir each of capacity 117,000 cbm to add a total storage capacity of 585,000 cbm.

  • In 2010 the fifth expansion phase was commissioned in both terminals (Ain Sukhna and Sidi Kerir) through the construction of one floating roof storage tank in Sidi Kerir terminal and 3 in Ain Sukhna terminal each of storage capacity of 117,000 cbm which added a total storage of 468,000 cbm to the system.

  • During 2013 phase 6 was introduced to serve the crude oil storage market by an additional 1,050,000 cbm through the construction of 6 floating roof storage tanks each of capacity 175,000 cbm and a 4.35 MW boosting pumping station.

 

Latest News |
Highlighter
Ain Sukhna Product Hub ASPH jetty contract - 2016-06-01
SUMED EGAS Contract - 2015-12-17
Ain Sukhna Product Hub ASPH - 2015-12-09
SUMED prepares for starting the detailed engineering of the LPG project - 2013-09-30
SUMED intends to develop a refined product and feedstock ... - 2013-08-15